Call for Laois estate built in the boom to be taken in charge

Landsdowne Close Portarlingtonplaceholder image
Landsdowne Close Portarlington

“Some of the estates take 17 or 18 years to take in charge,” meeting told.

An estate built in Celtic Tiger years still hasn’t been taken in charge because not all phases are complete, a meeting was told. 

Sinn Fein Cllr Aidan Mullins said the Lansdowne Estate in Portarlington had only half its lights working and there are manholes protruding four or five inches from the road surface. 

He tabled a motion asking “that Laois County Council commence the taking in charge of Lansowne Estate in Portarlington.”

In a written response, Evelyn Brownrigg in Laois County Council’s  Planning Department said: “To date we have not received a formal request from Kingscroft Developers to have this estate taken in charge as there are remaining phases to be constructed under Planning application 18 / 422. Once we have a request from either the developer or a plebiscite of owners within the estate relating to a completed phase of development, we can then initiate proceedings to commence the process.” 

Cllr Mullins said any further phases were separate planning applications and shouldn’t influence the existing estate. 

“Lansdowne Estate was built during the height of the boom and to me, the first phase of estate is completed,” he said. 

He said the road infrastructure was never finished and is in “an awful state” with manhole covers protruding from the roads. 

“Anyway I think the planners were asleep at the wheel when they gave planning permission, the road isn’t as wide as the footpath,” he said. 

Cllr Mullins said he would have a plebiscite completed in under a week. It will involve getting the backing and signatures from people living in the estate

“I am going to do that. I am not going to hang around for the process to be resolved,” he said. 

Fine Gael Cllr PJ Kelly described the response as “very unusual” in that the whole estate had to be completed. He said there would have been a deposit from the developer to ensure the estate is finished. Cllr said there could be ten phases to some plans but some of them are never completed. He offered his help to councillor Mullins with the plebiscite. 

Cllr Mullins said the bond would have lapsed years ago. He said up to 10 of the public lights are out in the estate for the past six months. 

“Half the estate is in darkness because it hasn’t been taken in charge,” said Cllr Mullins. 

“In fairness to the council, they are going to  step in and help,” he added. 

Fianna Fail Cllr Padraig Fleming said he fully supported the motion. 

“Some of the estates take 17 or 18 years to take in charge,” he claimed. 

Independent Cllr Ben Brennan took issue with the council response. 

He said he knew and estate which had been taken in charge before another phase was completed. “I can’t understand why this is different,” he said.   

  