Planning lodged for Portlaoise district heating centre to serve hospital, prison and homes


Fossil fuel free district heating centre based at Laois Sawmills would heat Portlaoise hospital, prison and many homes
A company is seeking planning permission from Laois County Council for a ‘district heating energy centre’ that will transform how the Dublin road side of Portlaoise heats itself, saving money and the environment.
The centre is proposed to be built beside Laois Sawmills off the Stradbally road in Ballymacken.
It will use excess heat from the dryers in the wood pellet factory, and waste timber from the sawmills, to heat water that will be piped into the town to heat homes and businesses.
District heating centres run all over Europe, serving 80 million people who don’t need heating systems in their own homes.
Its biggest customers will be the prison and Midlands Regional Hospital Portlaoise but homes in eastern Portlaoise will also get a chance to sign up to heat their homes for less money in an environmentally friendly way.
HeatGrid Ireland Limited, is applying for a 10-year permit to give it time to develop a district heating energy centre at Ballymackan, Portlaoise, Co. Laois and an insulated underground network pipeline over 4km long, in the townlands of Ballymackan, Ballymooney, Beladd, Kilminchy, Ballyroan and Borris Little in Portlaoise.
The district heating energy centre with a floor size of 1186 sq.m,will have a generated capacity of up to 11MW.
It would have a boiler room, biomass fuel store, storage room, admin block, staff welfare facilities, 15-metre thermal water tanks, 16-metre biomass fuel stacks, 16-metre gas boiler fuel stacks, electrostatic precipitators, gas boiler units, a gas fuel store, access track, and associated drainage, water and utility service infrastructure.


There would also be an external heat recovery unit measuring 14.75 metres.
The district heating network pipeline will be c. 4232m in length, running from the proposed energy centre under the R425, R445 and L6311 roads, with pipes to connect that hot water pipeline to sites/premises.
Its primary heat source will be waste heat recovered from the existing woodchip dryer stack at Laois Sawmills by the proposed External Heat Recovery Unit, which is expected to provide up to 50% of the annual heat demand depending on how much heat is available, and how often the sawmill is in operation.
Heat that would otherwise be lost to atmosphere will instead be captured and used. This recovered heat will be supplemented by two (2) biomass boilers, fuelled mainly by woodchip sourced directly from the adjacent sawmill during times with the output is low from the Heat Recovery Unit, and two (2) gas boilers providing backup and peaking capacity during periods of high demand.
The thermal storage tanks will allow recovered heat to be stored and released in line with network demand, making the most of the waste heat available from the sawmill. The energy centre will be unmanned for much of the time, with a maximum of six (6) staff on site at any one time and no public access.
The plan already has state support, with the announcement on October 1 by the Minister for Energy and Climate Darragh O’Brien, of €5m in support to plan nine such centres around Ireland, and a further €20 m down the line to fund constructions.
Laois TD Sean Fleming welcomed the news, explaining the details.
“This project in Portlaoise needs anchor customers to make it viable in the first instance. The 2 anchor customers are Government bodies; Portlaoise Hospital and Midlands Prison.
“Housing estates and businesses will be able to link into this new district heating system once it is constructed.
“It is important that the Government leads the way in the provision of these district heating systems which are cheaper to operate than using oil or gas.
“Yesterday in Dáil Eireann, as Chairman of the Oireachtas Infrastructure Committee, I spoke with the Chief Executive of the HSE specifically on this project who confirmed that they were very pleased to have Portlaoise Hospital included in this scheme. I also acknowledged the work that the HSE has been doing locally in recent times in preparation for this.
“I was pleased to meet with Laois Sawmills earlier this week. Laois Sawmills is one of the largest suppliers of wood pellets in the country and thousands of houses nationwide have installed wood pellet stoves in their homes in recent times.
“The raw materials for wood pellets is the unused timber/waste from sawmills. There is an abundance of this material in the country. Laois Sawmills are experts in drying out this product and turning it into wood pellets to sell for stoves in homes.
“I also spoke with the Minister for Energy, Darragh O’Brien this week who is fully supportive of this project and was very pleased to announce financial support.
“Overall, this is a great use of waste material. It is based on renewable energy and it will reduce our dependence on oil and gas. It will help decarbonise our energy system in the country and it is great to see Portlaoise will be playing a leading part in this.
“I look forward to this district heating system progressing and I look forward to when it is completed that many of the housing estates in Portlaoise that want to link into this will be able to do so,” Dep Fleming said.
The planning application includes multiple reports assessing its impact, including on the environment, on traffic, visual impact and noise.
A traffic report states that there will be a maximum of six staff on site at any one time, with no public access and only occasional service vehicle activity.
“The majority of biomass fuel will be sourced directly from the adjacent sawmill site, with the potential for occasional supplementary deliveries from off-site. Even under a worst-case scenario, such deliveries are estimated at approximately two truck movements per day”.
A planning decision is due by November 11, with any submissions accepted up to November 2.