"Incredible"; Laois/Offaly TD condemns 7 year delay of local Flood Relief


The TD discovered that the scheme is still at Stage 1, out of a 5 stage process.
Laois/Offaly TD Brian Stanley has called the 7 year delay in the Mountmellick and Portarlington Flood Relief Scheme “incredible”.
Deputy Stanley raised the Mountmellick and Portarlington Flood relief Scheme with the Chairperson of the OPW and Head of Flood Management Jim Casey when they appeared before the Dáil Public Accounts Committee (PAC). The TD discovered that the scheme is still at Stage 1, out of a 5 stage process.
Mountmellick is currently at the preliminary design stage. OPW have said that they are progressing that stage, with stage 1 construction is to commence in July 2025. Construction will likely take at least three years.
The Portarlington scheme is also at the Stage 1 preliminary design stage. The scheme will deliver protection to 72 properties. It is on schedule to submit for planning permission in quarter 1 next year, in February. Construction of the Portarlington scheme is to commence in the middle of July 2026 and will also likely take at least three years.
Deputy Stanley said that 7 years after Mountmellick flooded, it’s “incredible’’ that this is the case.
“The average duration of the scheme development and preliminary design phase is 48 months,” Deputy Stanley said.
“I understand what happens when you stop water from flooding one part of a town. In Mountmellick, for example, if you move it from Manor Road, you could finish up with it down in Acragar. There can be unintended consequences,” said the Deputy.
“The average length of construction is 36 months and handover of works can take 12 months. That means it takes 11 years, assuming everything goes according to plan. Mountmellick was badly flooded in November 2017, which is almost seven years ago, and there is not a shovel in the ground, to put it simply. What can be done to shorten that?”.
The public are looking at this. It takes 11 years. I hope I am wrong, but it would not be an exaggeration to say that this could drag on for 13 or 14 years. Houses and businesses on Manor Road, Derrycloney, Moore Street and Patrick Street were damaged.
I acknowledge that the County Council has done a lot of the work, widening channels, taking away debris and putting in screens.


Pictured; 2017 floods in Mountmellick
Mr. Jim Casey, Head of Flood Management at OPW, responded that ‘it is a concern for them’, and it is ‘undoubtedly a concern for residents’.
“It is not unusual in an international context. We visited Germany in the past 12 months and heard similar concerns,” said Mr Casey.
“There are measures you can bring forward to solve problems more quickly, maybe where problems are more easily defined and less complex.
There may be multiple sources of flooding. We must undertake detailed analysis and develop sophisticated hydrological and hydraulic modelling. Subsequently, we have to come up with a scheme that will actually solve the problem and will stand up to judicial reviews, legal challenges and so on,” Mr Casey finished.
Portarlington’s Flood Relief Scheme is costing an estimated €15 million, while The Mountmellick Flood Relief Scheme has a preliminary total project budget of €6.8 million.