In a big change from the decades that some residents of Celtic Tiger estates had to wait, a Laois housing estate that is less than five years old is expected to soon be taken in charge.
Residents have requested that final road surfacing be done urgently at Borris Meadows.
The 36 house development is owned by the Tuath Housing Agency for Laois County Council tenants.
They all moved in at the height of Covid-19 in 2020 and three years on, the finishing touches are being put to roads and pipes by the builder, the council has reported.
Cllr Caroline Dwane Stanley sought an update on the taking-in-charge progress of the estate off the Borris Road.
A detailed reply came from planning official Evelyn Brownrigg.
"Belgrave Construction have engaged J Conlon Construction to address the outstanding works and are currently on site to carry out repairs to a section of SW sewer, benching to SW manhole, minor repairs to footpaths, raising of ironwork prior to final surfacing , & construction of boundary wall.
"It is envisaged that these works should be completed in the next 3-4 weeks with the final road surfacing being done immediately after. Once fully completed we should be able to recommend the development to be taken in charge," she said.
Cllr Dwane Stanley said she is "absolutely delighted" with the progress.
"Some residents were in contact with me. A major concern for them was the last layer of tarmac. As you go out you go up on a bit of a ramp. They felt it was a bit of a hazard. It's a lovely area. Laois County Council has tenants in there with a housing body," she noted.
Cllr Willie Aird seconded.
"In fairness the builder is very cooperative. He has done a good job with the wall. I hope it is taken over very shortly," he said.