Portlaoise ESB substation upgrade to add capacity for 2,500 houses

ESB Pallas 38kV substationplaceholder image
ESB Pallas 38kV substation | ESB

The upgrade of the 38KV Pallas station is due to be completed in 12 weeks

An upgrade of an ESB’s station in Portlaoise will strengthen the network and provide additional capacity for the equivalent of 2,500 houses.

The doubling of the capacity of the Pallas 38Kv substation by replacing its two 5MVA(Megavolt Amperes) transformers with two 10MVA transformers. The work is taking place in stages with the first new transformer in place and due to be energised at the end of October and the second set to come online in 12 weeks.

Once commissioned, the final upgrade will deliver a total of 10 MVA additional installed transformer capacity, strengthening the network in Laois and supporting future residential, commercial, and industrial demand.

To put this in context, the upgrade will provide enough additional installed transformer capacity to support approximately 2,500 houses, including facilitating the electrification of heating and transport.

Capacity Deployment Manager, ESB Networks, James Finn, said: "This upgrade at the Pallas 38 kV Station is an important step in accelerating additional capacity for Portlaoise and the wider region, helping to support new homes, business growth and the continued development of local communities.

"By increasing the capacity of the existing network, through targeted strategic interventions, ESB Networks is enabling customers to connect sooner, while also preparing the system to support increasing electrification, including heat pumps and electric vehicles as Ireland progresses with its climate ambitions."

These works form part of ESB Networks’ wider programme of investments under Price Review 6 (PR6), to strengthen and build out the electricity network across the country, ensuring it can meet increasing demand while supporting Ireland’s housing and climate ambitions.

This work is in addition to a recent upgrade in Portlaoise which involved the uprating of two 31.5 MVA transformers to 63 MVA at the Portlaoise 110 kV Station, doubling capacity there and enabling new customer homes, businesses, and farms to connect to the electricity network.

ESB Networks also energised a new 110 kV station at Bracklone, near Portarlington, Co Laois, earlier this summer - the first of 30 new 110 kV substations planned under PR6 - which will benefit approximately 13,000 customers across the wider Co Laois and Midlands region.

Work is also continuing on the Laois-Kilkenny Grid Reinforcement Project, which includes the construction of a new substation at Coolnabacky, near Ratheniska, Co Laois, in order to boost electricity capacity in the Midlands and South East. The Laois-Kilkenny Grid Reinforcement Project is one of 29 priority transmission projects brought forward by EirGrid and being delivered by ESB Networks under PR6.